Dear Devotees,
The new temple project is progressing well, with significant advancements made over the last 6 weeks. Here's a summary of the recent developments:
1. Pyramid skylights have been installed
2. Electrical transformer is now in place
3. Storefront doors and glass windows are fitted
4. Walls for electrical panels have been constructed
5. Electrical connections from panels to rooftop units are complete
6. Roof drains tie in complete
7. Fire pump house vault installed
*Upcoming tasks to be completed in Phase II*
1. Construct pump house building
2. Starting Roof top units
3. Exterior thin brick mock up to be built
4. Power up exterior lighting
These achievements mark important milestones in the construction process. The project team is currently working on determining the costs for the next phase of construction. The plan is to start the Phase III in March, with an estimated completion period of 5-6 months.
Your continued support and assistance have been instrumental in bringing the project this far. The construction team's efforts, combined with the devotees' backing, have enabled steady progress towards realizing the new temple.
We extend our deepest gratitude to all the donors and devotees for their invaluable support in the construction of this temple, a new home for Sri Radha Vrindavana Natabara. Your selfless contributions are a sacred offering to the divine, and may the Supreme Lord bless you with unlimited mercy. Hare Krishna.